| Process |
|
- Controlled as per ISO-9001 requirements
- Quality Requirements as per IPC-A-610 (C) or as per the customer specifications
- Class of inspection as per the job requirement
|
| Non - Conformity |
- Handled as per ISO-9001 procedure & WIE Executive Procedure EP-10
|
| Traceability |
- In process batch card with each batch
- Lot code of components / material used
- In process tray slip with each tray
|
| Parts and Material Control |
- Approved Bill of Materials
- Inward QC performed
- Material marked and stored separately for each customer
|
| Packing, Material Handling and Storage |
- As per manufacturer’s specifications and section 3 of IPC-A-610 (C) standard (Table 3-4)
|
| Personnel Training |
- As per well defined procedure at all levels
- Cross functional training is conducted to instill multiple skills in operators
- Workmen are internally trained and qualified by ISRO to work on Hi-Rel jobs
|